Horizon for available capacity in work center in planning table and capacity planning

$
0
0

Hi experts,

 

When accessing to planning table for long term planning (MFS0), I observe that available capacity for work center stops about 2 years and 9 months after the beginning of the period.

 

It corresponds to 999 calendar days.

 

Note 1227020 says :

Moreover, in CRP, the maximum possible value for available capacity under work center (TC35A-PAANZ) is limited to 999 days. Hence the capacity data in planning table can be displayed only upto a maximum of 999 days only.

 

Do you confirm that :

    • available capacity is limited to 999 calendar days
    • capacity requirements are generated when scheduling planned orders up to 999 working days (maintained in OPU5)

 

If so, why available capacity at work center can be seen in CM38 (capacity planning for long term planning) much further ? Up to May 2019 in my case.

 

Thanx for your explanations.